These easy to follow step-by-step instructions will guide you through every step of the installation process of the SquidGee Dry™ System.
Download a PDF version of the SquidGee Dry™ Installation Guide to print out and have beside you when installing the system. (Download the latest version of Adobe Reader)
See all of the installation steps in video: basement waterproofing installation videos
1. Relieve Hydrostatic Pressure
Make weep holes into the cells of each block (4" to 6" in from each mortar-joint ) at the point where the floor and wall meet. Solid poured concrete walls have no cavities, so weep holes are not required. |
2. Prepare the Surface Properly
To properly bond and seal the system to the concrete floor, the floor area along the wall approximately 3" wide must be stripped to bare concrete. To remove all paint or tile adhesive, use a 3M metal paint stripper wheel with your electric drill. |
3. Clean the Surface Properly
It’s very important that you do this step properly. After floor area has been stripped, wash with clear water and sponge to remove all dirt and dust. When finished feel the area with your fingers for any loose grit left behind. |
4. SquidGee Dry SealOnce™
Angle cut the tip just under the cone shaped end. This will give the large opening needed for applying SquidGee SealOnce™ to all surfaces. One tube of SquidGee SealOnce™ is needed for each 4 ft 6 inch Main section. |
5. Placing Pre-molded Corners
Begin by placing pre-molded corner sections in all the corners. Mark the floor in front of the corners showing where the main sections will stop. |
6. Cut and Fit the Baseboard Sections
Now you are ready to cut and trial-fit the main sections along the basement walls. |